Power and Construction Group crews are scheduled to begin work on the night of July 18, 2022 for the NYPA-City of Batavia LED Street Light Project.

The tentative schedule is as follows:

  • Monday & Tuesday – start/finish Main Street and then start Oak Street.
  • Tuesday & Wednesday – finish Oak Street and then start Ellicott Street/Route 63.
  • Wednesday through Friday – finish Ellicott Street/Route 63 and all other cobra head street light locations.

Traffic delays should be expected; however, no street closures are anticipated at this time.

We apologize for any inconvenience and thank the public for their patience.

 

 

 